Preparing your site for shipping container delivery means picking a flat, firm, easily accessible spot, clearing the access route, checking council rules, and getting the ground level before the truck shows up. Get those basics wrong, and you’re looking at a container that won’t sit flat, doors that jam, a churned-up front lawn, or worse, a driver who turns around and leaves with your container still on the back. If you’ve ever had a supplier promise next-day delivery and then ring at 4 pm with some excuse about access, you’ll know how much a bit of upfront site prep saves you down the track.

This guide walks you through it the way we’d talk you through it on the phone. No fluff, just what actually matters when you’re getting a container dropped on your block in Mackay, the Whitsundays, the Bowen Basin, or anywhere else we deliver across Australia.

14+
Years delivering containers since 2011
5.0★
Google Reviews rating
Next Day
Coastal Qld container delivery

Why Site Prep Matters More Than Most People Realise

Most blokes think site prep is just “clear a spot and she’ll be right”. Then the tilt tray rocks up, the driveway’s too narrow, there’s a low branch in the way, and the driver’s standing there with his arms crossed waiting for a decision. Half a day gone.

Proper preparation does three things. It keeps the container level so the doors open and close properly for the long term. It protects your driveway, lawn, and underground services from a 30-tonne delivery vehicle. And it stops the container from sinking, twisting, or rusting out from the bottom because water’s been pooling under it for six months.

A container that’s sitting on uneven ground will rack. That means the door frame distorts and the doors won’t shut. We’ve seen people pay good money for a brand new shipping container and turn it into a leaky shed inside twelve months because they skipped the prep.

What People Assume vs What Actually Happens On Container Delivery Day

What people assume What actually happens
“The driver will sort the spot when he gets here.” Drivers won’t manoeuvre into unsafe ground. If the spot isn’t ready, the container goes back on the truck.
“A bit of soft grass is fine, it’s only sitting there.” A loaded 20ft container puts 6 to 8 tonnes through four small corner points. Soft ground sinks within weeks.
“My driveway can definitely handle a truck.” Most residential driveways aren’t rated for a 30-tonne delivery vehicle. Cracked concrete is a real risk.
“Council won’t notice a container on a private block.” Neighbours notice. One complaint and you’re explaining yourself with a compliance order in hand.
“I’ll just chuck it on the lawn and tidy it later.” Once a container’s loaded, moving it costs nearly as much as the original delivery. Get it right the first time.

Step 1: Choose The Right Spot On Your Block

Walk your property and pick a location that ticks four boxes: firm ground, level (or close to it), away from the house, and easily accessible for a delivery truck. The closer to the kerb the better, because every extra metre of truck access you need is another thing that can go wrong.

Think about how you’ll actually use the container day to day. A storage container that’s tucked behind the shed sounds clever until you’re walking 40 metres in the rain with a toolbox. Put it somewhere convenient, but somewhere the truck can get to without taking out your letterbox.

Quick Site Audit: Tick The Boxes Before You Book

Walk your block with this list in hand. If you can tick all eight, you’re ready to book the delivery. If you can’t, fix it before the truck arrives.

☐ Spot is level within about 25mm across all four corners
☐ Ground is firm and compacted, not soft or boggy
☐ Access route is at least 3.5m wide at every point
☐ No overhead power lines, branches, or eaves under 7m
☐ Council approval checked and confirmed
☐ Cars, trailers, bins, and ornaments are moved out of the way
☐ Drop spot is marked with stakes or paint
☐ At least 3m of clear space at the door end

Two or more empty boxes? Send us a photo on 1800 006 162 and we’ll tell you straight whether to push delivery back a few days.

Step 2: Check Council Approval And Any Zoning Restrictions

This one trips people up constantly. Local regulations vary between every single council in Queensland, let alone the rest of Australia. Some councils don’t care about a container on a rural block. Others will send a letter the week after delivery asking why you’ve got an unapproved structure.

Before you order, ring your local council and ask two questions: do I need approval for a shipping container on my property, and are there any zoning restrictions or setbacks I need to know about? Get the answer in writing if you can. Compliance is dull, but it beats a $2,000 fine and an order to remove the container.

For residential blocks, most councils have rules around how long a container can sit there, how close it can be to the boundary, and whether it counts as a permanent structure. Mining sites, rural properties, and commercial yards usually have more leeway.

Step 3: Measure The Access Route From Kerb To Drop Point

Aerial view showing a planned container location and truck access route on a property.

Grab a tape measure and walk the access route from the road to where you want the container to sit. You’re looking for three things:

  1. Width at the narrowest point (gates, fences, between trees)
  2. The turning radius that the truck needs to swing in and reverse
  3. Surface the truck is driving over (concrete, gravel, lawn, dirt)

For a 20ft container on a tilt tray, you need a clear run of around 20 metres of straight access behind the drop point, and a corridor at least 3.5 metres wide. A 40ft container needs more again. A side loader can drop in tighter spots but still needs room to deploy its arms.

If you’ve got a sloped driveway, soft lawn, or a narrow gate, send photos to your supplier before booking. We’d rather know upfront than have the driver turn around at your gate.

Step 4: Clear The Area Of Vegetation, Vehicles, And Clutter

Anything that’s not nailed down needs to be moved. That means:

  • Cars, trailers, boats, ride-ons
  • Garden ornaments, pot plants, hose reels
  • Irrigation lines, sprinkler heads, and exposed pipes
  • Removable fence panels (take them out, don’t just unlock them)
  • Low branches, shrubs, anything overhanging the access route

Vegetation is the silent killer. A branch that looks fine when you’re standing on the ground will scrape the side of a container off a high truck deck. Cut it back further than you think you need to.

Step 5: Level And Compact The Ground So The Container Sits Flat

The ground where the container lands needs to be level and firm. Doesn’t need to be perfect, but a container sitting on uneven, soft ground is asking for trouble.

Here’s the simple version:

  1. Clear the area down to bare dirt
  2. Check it with a long spirit level or a string line and stakes
  3. Add or remove soil until the four corners where the container will sit are within about 25mm of each other
  4. Compact the soil with a hand tamper, plate compactor, or by driving over it with a loaded vehicle a few times

The four corner castings of the container carry all the weight. If those four points are sitting on firm, level ground, you’re sweet. If one corner’s on soft dirt, the container will sink unevenly, and the doors will stop closing within a few months.

✓ Ground that WILL hold a container ✗ Ground that WILL NOT
Compacted road base or gravel pad, 100mm deep Fresh topsoil or loose backfill from recent landscaping
Existing concrete slab in good condition Cracked or honeycombed concrete with hollow spots
Dry, compacted clay or natural firm dirt Wet clay, recently saturated ground, or lawn over fill
Treated hardwood sleepers on firm base Pavers or bricks loose-laid on sand
Black soil after a long dry stretch (with sleepers under corners) Black soil during or after wet season without footings

Step 6: Decide On A Foundation: Slab, Gravel, Or Timber Sleepers

You’ve got three sensible foundation options depending on how long the container is staying and what you’re using it for.

Foundation Best For Cost Drainage
Concrete slab Permanent placement, offices, workshops Highest Good
Gravel pad Medium to long-term storage Mid range Excellent
Timber sleepers or concrete blocks under the corners Hire, short-term, or temporary use Lowest Very good

A concrete slab is the gold standard, but it’s overkill for a container you’re hiring for six months. For most residential and site jobs, timber sleepers or precast concrete blocks under each of the four corner castings are perfect. It keeps the container off the ground, lets air circulate underneath, and stops the floor from rusting out.

A gravel pad is the sweet spot for medium-term storage. Spread 100mm of road base or 20mm crushed gravel over the prepared area, compact it, and you’ve got a stable, well-drained foundation that costs next to nothing.

Access Width Required By Container Size

Approximate minimum corridor width for safe container delivery on a tilt tray. Side loader needs roughly the same as the container length plus 1m.

6ft container (tight access)2.5m
10ft container3.0m
20ft container (tilt tray)3.5m
20ft container (HIAB)4.0m
40ft container (semi-trailer)4.5m+

Tight site? Send us a photo or video walk-through. A side loader can drop a 20ft container into a space barely wider than the container itself, where a tilt tray simply won’t fit.

Step 7: Confirm Overhead Clearance For Trees And Power Lines

Site inspection checking overhead clearance before container delivery.

Look up. A tilt tray delivering a 20ft container needs around 7 metres of overhead clearance when the bed is tilted. Power lines, branches, eaves, carport roofs, washing lines, you name it.

Power lines are the dealbreaker. If there’s a power line crossing the access route at a low height, the driver will refuse the job, and rightly so. Get Energex or Ergon out to check the height if you’re unsure, or pick a different spot.

Step 8: Match The Right Truck To Your Site (Tilt Tray, Side Loader, Hiab)

The truck has to suit the site as much as the container. Here’s the quick guide:

  • 6ft, 8ft, and 10ft containers: usually delivered on a small tilt tray, good for tight residential blocks
  • 20ft container: standard tilt tray or HIAB truck, needs decent access
  • 40ft container: large tilt tray or semi-trailer, needs a long straight run and plenty of turning room

A side loader is the magic option for tight spots. It picks the container off its own deck and places it sideways, meaning it can drop into a space barely wider than the container itself. They cost a bit more to hire, but they save you on sites where a tilt tray simply can’t fit.

Send your supplier photos of the access and the drop point. A good supplier will tell you straight up which truck will work and which won’t.

🚛
Tilt Tray
Bed angles up, container slides off. Most common method for 10ft to 40ft drops on standard sites.
🏗️
Side Loader
Lifts and lowers the container sideways using onboard cables. Best for tight or fenced sites.
⚙️
HIAB / Crane Truck
Onboard crane lifts the container into place. Good for elevated spots or over fences.
🚚
Semi-Trailer
For 40ft and high cube containers on commercial or mine sites with long, straight access.

Step 9: Plan For Drainage So Water Flows Away From The Container

Water pooling around or under a container will rust it out from the bottom in a couple of years. Up here on the Mackay coast, with the wet season dumping the kind of rain it does, drainage is not optional.

Slope the ground so water runs away from the container, not towards it. If you’re on flat ground, dig a shallow swale on the uphill side to divert runoff. Don’t put the container at the bottom of a slope where stormwater collects. And keep it off the ground using your sleepers or blocks so there’s airflow underneath.

Step 10: Mark The Exact Drop Position With Stakes Or Paint

When the truck arrives, the driver doesn’t want to be guessing where you want it. Mark the four corners of where the container should sit with wooden stakes, marker paint, or even pegs with flagging tape.

Stand back and look at it from a few angles. Make sure the doors will open in the direction you want, and there’s enough room to swing them fully open without hitting a fence or wall. The doors swing out about 2.4 metres, so leave at least 3 metres of clear space at the door end.

Your 3-Step Quick-Start Process

If you read nothing else, do these three things:

Step 1: PLAN Step 2: PREP Step 3: POSITION
Pick the spot, check council rules, measure the access route, and send photos to your supplier. Clear the area, level and compact the ground, lay your footings, and mark the corners. Confirm the truck type, make sure the route is clear on delivery day, and stand back while the driver does their thing.

Nail those three, and you’ve handled 90% of what can go wrong.

What Happens When You Book A Container Delivery With Us

No surprises, no chasing for updates. Real person on the phone from quote to drop-off.

01
Quick chat & quote
Tell us size, location, and how long you need it. Send a photo of the drop spot if you can.
02
Site check & truck match
We confirm tilt tray, side loader, or HIAB based on your access. No guesswork on delivery day.
03
Delivery scheduled
Next-day to most coastal Qld locations. We ring before the truck leaves the yard so you know when to be onsite.
04
Drop-off & sign-off
Driver places, levels, and walks the container with you. You sign off only when you’re happy with it.

What To Check Straight After The Container Is Offloaded

Don’t sign off and walk inside. Spend ten minutes with the driver and check:

  • All four corners are sitting flat on your footings, no gaps
  • The container is level end to end and side to side
  • The doors open and close smoothly with no binding
  • The locking bars operate properly
  • No obvious damage to your driveway, lawn, or any underground services
  • The container itself is the grade and condition you ordered

Newly prepared ground sometimes settles after a week or two, especially after the first heavy load goes in. Re-check the level once you’ve loaded it up and pop a sleeper or shim under any corner that’s dropped.

Since 2011
Mackay yard, local crew
100%
Australian owned & operated
BHP, Thiess, QR
Trusted by major mining & rail
6ft to 40ft
Every size in stock now

Site Prep Tips For Mackay, The Whitsundays, And Rural Qld Blocks

Finished shipping container installation on a stable, level foundation.

A few things specific to our patch up here. Cyclone season runs from November to April, so if you’re getting a container delivered between those months, think about anchoring or tying down. An unanchored 20ft container is a 2-tonne projectile in a Category 3 wind.

Black soil country, like a lot of the Bowen Basin and out around Clermont, moves like crazy with the wet and dry cycle. Concrete blocks or timber sleepers work better than a slab because you can re-level them. A slab on black soil will crack within a couple of seasons.

For remote rural and mine site deliveries out around Moranbah, Glenden, Nebo, or Collinsville, ground conditions after rain can be the difference between a successful drop and a bogged truck. Give the access road a few dry days if you can, and let your supplier know if there’s been recent rain.

Container Delivery Areas We Cover Across Queensland

From Mackay yard, we deliver containers next-day to most coastal Queensland locations and run regular drops out to the mining towns. If your suburb or site isn’t listed, give us a call. We almost certainly service it.

✓ Mackay
✓ North Mackay
✓ South Mackay
✓ East Mackay
✓ Andergrove
✓ Glenella
✓ Bucasia
✓ Rural View
✓ Sarina
✓ Proserpine
✓ Airlie Beach
✓ Bowen
✓ Collinsville
✓ Glenden
✓ Moranbah
✓ Nebo
✓ Clermont
✓ Carmila

Mackay’s Trusted Container Delivery Specialists Since 2011

Book Container Delivery That Actually Turns Up

Free quote in under an hour. Real person on the phone, not an offshore call centre. Next-day delivery to most of coastal Queensland, with stock ready in 6ft, 8ft, 10ft, 20ft, and 40ft.

Container Delivery: Common Questions

How much does container delivery cost in Mackay?

It depends on the container size, your distance from our Spiller Ave yard, and the truck type the site needs. Most residential drops inside Mackay sit in a low, predictable range. Out to the Bowen Basin or the Whitsundays it scales with the kilometres. Ring us with your suburb and we’ll give you a flat price on the spot, no surprises on the day.

Do I need council approval before a container is delivered?

For temporary placement on rural and mining sites, usually no. For permanent residential placement, most Queensland councils want approval or at least notification, with rules around setbacks, time limits, and whether the container is classed as a structure. Ring your local council first. It takes ten minutes and saves grief later.

How long does a container delivery actually take?

From the truck arriving on site to the container being placed and signed off, around 20 to 40 minutes for a standard tilt tray drop. Side loader and HIAB jobs take a bit longer, usually under an hour. Add time on top if the site needs cleared or repositioned, which is why doing the prep beforehand saves real money.

Can a container be delivered onto grass or a lawn?

Short answer, yes, but only if the ground underneath is firm and the lawn isn’t recently saturated. We strongly recommend timber sleepers or concrete blocks under the four corner castings, not the container sitting straight on grass. Grass holds moisture, the floor rusts, and within a year you’ve got a problem you can’t fix without lifting the container.

What’s the difference between a tilt tray and a side loader for container delivery?

A tilt tray angles the bed and slides the container off, which needs roughly 20m of straight access behind the drop point. A side loader lifts the container off the side of the truck using cables, so it can drop into a space barely wider than the container itself. Side loaders cost a touch more but they save jobs that a tilt tray simply can’t do.

How much clearance do I need above the container drop spot?

Around 7m of clear overhead space for a tilt tray to fully extend. That clearance has to be clean of power lines, branches, washing lines, carport roofs, anything. If you’re not sure about a power line height, ring Ergon or Energex and get them out before you book delivery.

Can the container be moved after it’s been placed?

Yes, but it costs about the same as a fresh container delivery. The truck has to come back out, lift it, reposition or reload, and drop it again. This is the main reason we push so hard on getting the spot right the first time. If you’re unsure, send us photos before you book and we’ll mark up the best drop position for you.

Do you offer next-day container delivery to mine sites in the Bowen Basin?

In most cases, yes. Moranbah, Nebo, Glenden, Collinsville, and Clermont are all on regular delivery runs from our Mackay yard. If you need stock urgently for a site shutdown or a project mobilisation, ring early in the day and we’ll usually have a truck rolling by next morning.

Need A Container Delivered The Right Way?

We’ve been delivering containers across Mackay, the Whitsundays, the Bowen Basin, and the rest of Australia since 2011. Local yard, local team, real person on the phone, and a tilt tray that turns up when we say it will.

If you want a hand working out the right size, the right truck, or the right foundation for your site, give us a ring on 1800 006 162 or send through a quick photo of your spot and we’ll tell you straight whether it’ll work. New and used containers in 6ft, 8ft, 10ft, 20ft, and 40ft, ready to go in stock right now.